House naqsha approval in Pakistan: who, what and how
Which authority approves your plot, the documents usually needed and the steps from drawing to completion certificate.
Before construction starts, your house drawing (naqsha) must be approved by whoever controls building in your area. Building without approval can lead to fines, sealing, problems with utility connections and trouble when you sell. The exact fees and rules change by authority and plot, but the process is similar everywhere.
Who approves your naqsha?
| WHERE YOUR PLOT IS | WHO APPROVES |
|---|---|
| Lahore | LDA (Lahore Development Authority) in its controlled areas |
| Karachi | SBCA (Sindh Building Control Authority) |
| Islamabad | CDA (Capital Development Authority) |
| Rawalpindi | RDA (Rawalpindi Development Authority) in its controlled areas |
| Faisalabad | FDA (Faisalabad Development Authority) |
| Multan | MDA (Multan Development Authority) |
| Peshawar | PDA (Peshawar Development Authority) |
| Private housing societies | The society’s own town planning office |
| Cantonment areas | The cantonment board |
| Outside these limits | The local municipal committee or tehsil council |
If you are not sure, ask the society office or the nearest authority office which body controls your plot before you pay for drawings.
Documents usually needed
- Proof of ownership: registry, transfer letter, allotment letter or fard, as applicable
- Owner’s CNIC copies
- Possession letter, NOC or site plan from the society, where applicable
- Architectural drawings (plans, elevations, sections) signed by a registered architect
- Structural drawings and calculations signed by a PEC-registered engineer, especially for multi-storey buildings and basements
- Paid fee challans and the authority’s application forms
The usual steps
- Check the bylaws for your plot: setbacks, coverage, height, number of storeys and parking.
- Get the drawings made to those bylaws, with the structure designed by an engineer.
- Submit the file with documents and fees.
- Answer objections, if any, with revised drawings.
- Receive the approved plan and keep a copy on site.
- Build as approved. Major changes need a revised approval.
- Apply for the completion certificate when the house is finished.
Common reasons files get stuck
- Drawings that ignore setbacks or height limits
- Ownership papers not matching the applicant
- Missing engineer’s signature or calculations
- Changes during construction that were never approved
RENOBILD prepares the authority file with the drawings and follows it while the soil test and utility applications run in parallel; approval usually takes one to two months of the overall timeline. See the full house construction timeline.
گھر کا نقشہ پاس کروانے کا طریقہ
تعمیر شروع کرنے سے پہلے نقشہ اس ادارے سے منظور کروانا ضروری ہے جس کے علاقے میں آپ کا پلاٹ ہے، جیسے لاہور میں ایل ڈی اے، کراچی میں ایس بی سی اے اور اسلام آباد میں سی ڈی اے۔ سوسائٹی میں سوسائٹی کا دفتر نقشہ پاس کرتا ہے۔ ملکیت کے کاغذات، شناختی کارڈ، رجسٹرڈ آرکیٹیکٹ اور انجینئر کے دستخط شدہ نقشے اور فیس عموماً درکار ہوتی ہے۔ گھر مکمل ہونے پر کمپلیشن سرٹیفکیٹ بھی لیں۔
Questions people ask
Who approves house plans in Lahore?لاہور میں نقشہ کون پاس کرتا ہے؟
In its controlled areas, the Lahore Development Authority (LDA). Plots in private housing societies are approved by the society, and cantonment plots by the cantonment board.
Who approves building plans in Karachi?کراچی میں نقشہ کون پاس کرتا ہے؟
The Sindh Building Control Authority (SBCA), except where a cantonment board or a society controls building.
Can I build first and get approval later?کیا پہلے گھر بنا کر بعد میں نقشہ پاس کروا سکتے ہیں؟
It is risky. Unapproved construction can be fined or sealed and can cause problems with utility connections and resale. Get approval before you start.