Grey structure checklist: check every stage before it is covered
What to check on site from digging to plaster, so hidden mistakes do not end up inside your walls.
Grey structure is the part of the house you cannot change later: foundation, columns, beams, slabs and walls. Mistakes here are hidden by plaster and paint, so check each stage before the next one covers it. Use this list on site, and ask your engineer to sign off each stage.
1. Before digging
- Approved drawings: architecture and structure, signed by a registered architect or PEC engineer.
- Soil test for anything above a simple single storey, or where the ground is filled, wet or saline.
- Plot levels, road level and neighbour walls recorded with photos.
2. Foundation and plinth
- Trench depth and width as per the drawing; loose soil removed and the bottom compacted.
- Lean concrete (blinding) under footings.
- Steel checked before concrete: bar size, spacing and cover blocks under the bars, as per the drawing.
- A proper damp-proof course (DPC) at plinth level. Missing DPC is the main cause of rising damp.
- Use sulphate-resisting cement below ground where the soil is saline, if your engineer advises it.
3. Columns, beams and slabs
- Count and measure the bars against the drawing before every pour: size, number, stirrup spacing and lap lengths.
- Concrete cover kept with spacer blocks, commonly about 3/4 inch in slabs and 1.5 inches in columns, as your drawing says.
- Formwork straight, strong and propped; no gaps that leak cement paste.
- Electrical conduits and plumbing sleeves placed before the slab is poured.
- Concrete mixed in the ratio on the drawing (or ready-mix with a delivery slip), poured continuously and vibrated.
- Cube samples taken from every slab and tested at 7 and 28 days.
- Curing: keep concrete wet for at least 7 days, longer in hot weather.
- Do not remove slab props until the engineer says so; commonly two weeks or more.
4. Brickwork and plaster
- Bricks soaked before laying; joints full and about 3/8 inch thick.
- Walls checked for plumb and line every few courses.
- Lintels over every door and window.
- Plaster only after conduits and pipes are fixed and tested; plaster kept wet for several days.
5. Records to keep
Ask for steel mill certificates, cement batch photos, cube test results and a photo set of the steel before every pour. These cost almost nothing and prove what is inside your walls. RENOBILD clients get all of them, with a progress report every Friday. Our grey structure rate guide shows what this stage costs. Before the first pour, read foundations and soil tests.
گرے اسٹرکچر چیک لسٹ
گرے اسٹرکچر گھر کا وہ حصہ ہے جو بعد میں بدلا نہیں جا سکتا۔ ہر مرحلہ اگلے مرحلے سے پہلے چیک کریں: منظور شدہ نقشہ، مٹی کا ٹیسٹ، بنیاد اور ڈی پی سی، سریے کا سائز اور فاصلہ، کنکریٹ کور، کیوب ٹیسٹ اور کم از کم سات دن کیورنگ۔ سریے کے مل سرٹیفکیٹ اور کیوب ٹیسٹ کے نتائج اپنے پاس رکھیں۔
Questions people ask
How many days should concrete be cured?کنکریٹ کو کتنے دن پانی دینا چاہیے؟
Keep it wet for at least 7 days, longer in hot weather. Curing decides how much of the design strength the concrete actually reaches.
What is a cube test?کیوب ٹیسٹ کیا ہوتا ہے؟
Small concrete cubes are filled from the same batch as the slab and crushed in a lab at 7 and 28 days, to prove the concrete reached its design strength.
When can slab supports be removed?لینٹر کے نیچے سے سپورٹ کب ہٹائیں؟
Only when the engineer says so; commonly two weeks or more, depending on span, weather and cement.