Pouring the roof slab: checks before, during and after

Shuttering, steel, concrete and curing: the slab checklist that prevents sagging, cracks and leaks.

RENOBILD engineering team · Updated 23 November 2026

The RCC roof slab ties the whole house together and carries everything above it. Mistakes here are expensive to fix and can be dangerous. Most problems come from three things: weak shuttering, wrong steel and poor curing.

Before the pour

  • Shuttering (formwork) is level, tight and strong, with props on firm ground and braced
  • Steel size, number, spacing and cover blocks match the structural drawing
  • Extra bars at supports and around openings are in place
  • Electrical conduits, fan boxes and plumbing sleeves are fixed before the pour
  • Your engineer checks and signs off before concrete starts

On pour day

  • Use the concrete mix the engineer specifies, with measured water: extra water weakens concrete
  • Pour in one continuous operation where possible; plan joints with the engineer if not
  • Compact the concrete with a vibrator so there are no honeycombs
  • Make test cubes from the same concrete for strength testing

After the pour

  • Start curing as soon as the surface has set and keep it wet for the period your engineer specifies, usually at least a week
  • Use ponding or wet hessian; a few sprinkles a day are not enough in summer heat
  • Do not load the slab with bricks or steel in the first days
  • Remove props only when the engineer says; slab props stay longer than side shuttering

Warning signs

  • Sagging or cracks in the slab soon after props are removed
  • Rust stains or exposed steel on the underside
  • Honeycombs (gaps) at beams and column tops
  • Water seeping through the slab after rain

Call your structural engineer if you see any of these. Then protect the slab from the weather: see our roof waterproofing guide, the grey structure checklist and the foundation guide.

چھت (لینٹر) ڈالنے کی چیک لسٹ

لینٹر ڈالنے سے پہلے شٹرنگ کی مضبوطی اور لیول، سریے کا سائز، فاصلہ اور کور بلاک ڈرائنگ کے مطابق چیک کریں اور بجلی کے پائپ پہلے لگائیں۔ انجینئر کی منظوری کے بعد کنکریٹ ڈالیں، پانی ناپ کر ڈالیں اور وائبریٹر استعمال کریں۔ کم از کم ایک ہفتہ یا انجینئر کے بتائے دنوں تک ترائی کریں اور سپورٹ انجینئر کے کہنے پر ہی ہٹائیں۔

Questions people ask

How long should a roof slab be cured?لینٹر کی ترائی کتنے دن کریں؟

Keep it continuously wet for the period your engineer specifies, usually at least seven days, longer in hot, dry weather.

When can slab shuttering be removed?لینٹر کی شٹرنگ کب کھولیں؟

Side shuttering comes off early, but props under the slab stay longer. Remove them only when your engineer approves, based on span and concrete strength.

Why does adding extra water to concrete matter?کنکریٹ میں زیادہ پانی کیوں نقصان دہ ہے؟

Extra water makes concrete easier to pour but weaker and more porous, which leads to cracks and leaks.