How long does it take to build a house in Pakistan?

The six stages from first visit to keys, the order of work on site and what usually causes delays.

RENOBILD engineering team · Updated 23 November 2026

Most families underestimate how long a house takes, then rush decisions on site. Building a 5 marla double-storey house properly takes about 10 to 12 months from the first visit to the keys. Larger houses take 12 to 15 months.

The six stages

STAGETIMEWHAT HAPPENS
Site visit2 daysPlot, road, levels and neighbours measured; we listen to how your family lives.
Concept3–5 daysTwo layouts with 3D views and a first budget.
Design set2–3 weeks24 sheets, calculations, renders and a measured BOQ.
Approval1–2 monthsAuthority file prepared and followed; soil test and utilities in parallel.
Construction8–10 monthsGrey structure, then finishing. Steel checked before every pour.
KeyshandoverA House File with as-built drawings and photos of every hidden pipe and wire.

Inside construction: a typical order

  1. Excavation, foundation and plinth with the damp-proof course
  2. Ground-floor columns, beams and slab, then the next floors
  3. Brickwork, lintels and the roof
  4. Electrical conduits, plumbing lines and plaster
  5. Roof waterproofing and heat insulation
  6. Flooring, doors, windows and kitchen
  7. Paint, fittings, testing and final cleaning

What slows a house down

  • Changing the design after construction starts
  • Late decisions on tiles, kitchen and fittings
  • Payment gaps that stop the labour
  • Rain, extreme heat and holidays such as Eid
  • Material shortages or price jumps

How to stay on time

Finish the design and the BOQ before the first brick, choose finishes early, and pay monthly against measured work so the site never stops. Check the quality of each stage with our grey structure checklist, and plan your budget with the 2026 cost guide.

گھر بنانے میں کتنا وقت لگتا ہے؟

پانچ مرلہ ڈبل اسٹوری گھر صحیح طریقے سے بنانے میں پہلی ملاقات سے چابی تک تقریباً دس سے بارہ مہینے لگتے ہیں۔ ڈیزائن اور منظوری میں دو سے تین مہینے اور تعمیر میں آٹھ سے دس مہینے۔ ڈیزائن میں بار بار تبدیلی، فیصلوں میں دیر اور ادائیگی میں وقفہ کام روک دیتے ہیں۔ پہلی اینٹ سے پہلے ڈیزائن اور بی او کیو مکمل کریں۔

Questions people ask

How long does a 5 marla house take to build?5 مرلہ گھر کتنے مہینے میں بنتا ہے؟

About 10 to 12 months in total: 2 to 3 months for design and approval, then 8 to 10 months of construction.

How long does grey structure take?گرے اسٹرکچر میں کتنا وقت لگتا ہے؟

For a 5 marla double-storey house, usually about 4 to 5 months, depending on weather, labour and payments.

What delays house construction most?تعمیر میں سب سے زیادہ دیر کس وجہ سے ہوتی ہے؟

Design changes after work starts, late decisions on finishes and gaps in payment that stop the labour.

Need help on your own house?

Send 3–4 photos or your plot size on WhatsApp

We reply with what it probably is and the next step. Across Pakistan; overseas clients by video call.