Plaza construction cost in Faisalabad, 2026
A trade-by-trade measured BOQ for a 10 marla corner plaza: basement + ground + 8 floors, shops and offices, priced at Faisalabad rates for November 2026.
10 marla corner plaza: what each trade costs
Our design for a 35 x 65 ft corner plot: basement + ground + 8 floors, shops at street level and offices above, about 17,295 sq ft built. Quantities come from the 3D structural model (about 37,600 cft of concrete and 79 tonnes of steel). Land, design fees, finance cost and authority fees are not included.
| TRADE | AMOUNT | RS / SQ FT BUILT |
|---|---|---|
| Preliminaries, site office, hoist and crane (20 months) | Rs 2.00 crore | 1,156 |
| Excavation, shoring and dewatering for the basement | Rs 0.41 crore | 239 |
| Concrete (RCC): raft, columns, shear walls, slabs | Rs 3.68 crore | 2,128 |
| Reinforcement steel (about 79 tonnes) | Rs 2.42 crore | 1,400 |
| Masonry, plaster and waterproofing | Rs 0.93 crore | 539 |
| Facade: curtain wall, shopfronts, stone, fins | Rs 5.09 crore | 2,945 |
| Finishes: office floors, ceilings, toilets, common areas | Rs 1.99 crore | 1,153 |
| Doors (fire-rated) and railings | Rs 0.81 crore | 471 |
| Passenger lift, 8 persons, 11 stops | Rs 1.10 crore | 636 |
| Electrical, transformer, generator, solar, ELV | Rs 3.14 crore | 1,815 |
| Fire fighting and plumbing | Rs 1.13 crore | 652 |
| Air-conditioning, VRF (optional, often tenant scope) | Rs 1.01 crore | 587 |
| External works | Rs 0.06 crore | 33 |
| Contingency 7% | Rs 1.67 crore | 963 |
| Contractor overhead and profit 10% | Rs 2.55 crore | 1,472 |
| Total construction cost | ≈ Rs 28.0 crore | ≈ 16,190 |
Taller is not always better
On this 10 marla plot our feasibility study found that building B + G + 8 to sell does not pay back: sales do not cover land, construction and finance. Building G + 3 on your own land for shops and offices on rent is the option we recommend to start with. Grey structure alone (trades A to E with markups) is about Rs 11.1 crore, or Rs 6,430 per sq ft. Approval, commercialisation and parking fees depend on the FDA demand notice and can be large, so we check them before design.
Download the plaza project dossier (PDF) or see today's material rates.
One team from feasibility to handover
Feasibility
What the plot can carry: floors, shops, parking and the rent it can earn.
Design and approvals
Architecture, structure, services and approval drawings.
Measured BOQ
A priced quantity list before construction starts.
Construction
Grey structure and finishing, with lab cube tests for every slab.
No big advance. Pay for measured work.
- Only a 10% security at signing, adjusted in the last bill
- One bill a month, for work measured with you at BOQ rates
- Payment by bank transfer to the company account, with a numbered receipt, never cash to workers
- You keep 5% of every bill as retention until handover and the defect period
Promises you can check
Every promise is a clause in your stamp-paper agreement, and each one leaves proof you can check yourself.
Measured price
The BOQ lists every item with its measurement. Rates are locked in the contract.
Pay for work done
At month end we measure the work with you, on site or on video, and bill only that work.
Proof of materials
Mill certificate for every steel lot, batch photos for cement, a lab cube test for every slab.
Report every Friday
Photos, a short video, what was done this week and what comes next, on WhatsApp.
We pay if we are late
0.1% of the contract price for every week of delay within our control, up to 3%.
Written guarantees
5-year maintenance with a free yearly check-up, 5 years on waterproofing, 15 years on structure.
Straight answers
How much does it cost to build a plaza in Faisalabad in 2026?Faisalabad mein plaza banane ka kharcha kitna hai?
Our measured BOQ for a 10 marla corner plaza with basement + ground + 8 floors (about 17,295 sq ft built) comes to about Rs 28 crore, or about Rs 16,190 per sq ft, at November 2026 rates. Land, design fees, finance cost and authority fees are extra.
What is the per sq ft rate for commercial construction?Commercial building ka per square foot rate kya hai?
About Rs 16,190 per sq ft complete for this design, including a curtain-wall facade, lift, fire fighting, generator and finished common areas. The grey structure alone is about Rs 6,430 per sq ft.
Which costs the most in a plaza?Plaza mein sab se zyada kharcha kis cheez par hota hai?
In this design the facade (curtain wall, shopfronts, stone and fins) is the largest trade at about Rs 5.1 crore, followed by concrete at Rs 3.7 crore and electrical with transformer and generator at Rs 3.1 crore.
How many floors should I build on a 10 marla plot?10 marla plot par kitni manzil banani chahiye?
It depends on whether you sell or rent. Our feasibility study found that B + G + 8 to sell does not pay back on a 10 marla plot, while G + 3 on your own land for rent is viable. We check this before you spend on design or approvals.
How much advance do you take?Advance kitna dena hoga?
Only a 10% security at signing, adjusted in the last bill. After that you pay one bill a month for work measured with you at BOQ rates, by bank transfer to the company account, and you keep 5% of every bill as retention.
What guarantees do you give, in writing?Guarantee kitne saal ki hai?
A 5-year maintenance guarantee with a free check-up visit every year, 5 years on roof and bathroom waterproofing and 15 years on structure, written into the stamp-paper agreement. If you sell the house, the guarantees pass to the new owner.
Is RENOBILD a registered company?Kya RENOBILD registered company hai?
Yes. RENOBILD (SMC-Private) Limited is incorporated with the SECP (CUIN 0366509, 16 Nov 2026) and registered with FBR (NTN K673445). You can verify the company on the SECP website.
Send your plot size or 3–4 photos on WhatsApp
We reply with the next step and a visit time. Overseas clients by video call.